3. RECONSTRUCTION

At last! The Studio and Gallery Begin to Emerge! (October-November 2018)

The studio expansion to the former Repair Shop begins to define the future Design Shop for LWSI. A series of large ‘garage door’ openings will provide a light-filled work environment. The former Showroom and miscellaneous office spaces have been opened up to create a flowing open space incorporating a conference room, gallery/pop up social space, restrooms, and secondary lounge areas. The new, leveling concrete floors provide 100% accessibility throughout the building. Of course, all of the mechanical, electrical, communications, fire and plumbing systems are being completely modernized.

Pouring new floors!

Pouring new floors!

The future gallery space beginning to take shape.

The future gallery space beginning to take shape.

Prepping the west wall of the studio for the new extension and view to future fab lab beyond.

Prepping the west wall of the studio for the new extension and view to future fab lab beyond.

Framing in studio

Framing in studio

Foundation for new addition to studio

Foundation for new addition to studio

Foundation goes in

Foundation goes in

Framing begins

Framing begins

The basic structure of the addition is revealed

The basic structure of the addition is revealed

Creating a larger open space and windows within the conference room.

Creating a larger open space and windows within the conference room.

Framing and systems are installed

Framing and systems are installed

Electrical

Electrical

Network

Network

After spray insulation drywall installed throughout

After spray insulation drywall installed throughout

Studio space is coming together

Studio space is coming together